Pure Green Consulting has been commissioned as Owners Engineer for Stavro Wind Farm in Northern Sweden. The project is to comprise 62 wind turbine generators, including 92km of cable infrastructure etc..... split between 2 sites.
Site works to date include tree felling for areas of future development, road widening works and ongoing site investigation to obtain design parameters for civil works.
A site inspection was undertaken, including existing site roads, areas of current activity, the substation locations and existing site roads to be utilised by the development. A meeting was then held in YIT's newly established site offices with the project team and principle contractor.